performance analysis of a solar chimney power plant in the southwestern region of algeria
2009
Renewable and Sustainable Energy Reviews
Salah Larbi; Amor Bouhdjar; Toufik Chergui
10.1016/j.rser.2009.07.031
Summary
Assesses whether a solar chimney power plant at Adrar, in Algeria's sunny southwest, could supply electricity to remote villages. Estimates based on monthly mean sunshine give an output of roughly 140 to 200 kW over the year, which the authors judge sufficient for the needs of isolated communities.